Mastclimbers

Project Description

2 x Twin MSM Super Mastclimbers, 24m long x 50m high deployed for cladding and pipework. The base of each drive unit had to be built on shoring due to site symops and required significant temporary works engineering to be supplied. Each had a 1,800kg payload and enabled 6 persons to work safely on each platform at any one time.

Mastclimbers were chosen by the client late in this data centre project and enabled the contractor to catch up with the project work schedule. EWP’s were the initially the chosen access method and proved ineffective when compared with Mastclimbers in this application due to their limited platform size, load capacity and a hire cost per EWP that was Triple the hire cost of each mast climber per week.